02 · Financial & Monitoring / Reporting · Enterprise

Monitoring & Reporting System for Financial and Regional Enterprise

Requirement workshops, process mapping, wireframes, and delivery tracking for operational reporting.

Domain

Financial & Monitoring / Reporting

Client type

Financial and regional enterprise (anonymized)

Duration

9-12 months

Role

PM / BA

Problem

Reporting rules came from several operational units, and the data dependencies needed to be clear before development and testing began.

What I did

  • Ran requirement gathering sessions and checked technical feasibility with engineering early.
  • Drew process flowcharts, use cases, and low-fidelity wireframes so users could confirm report layouts before UI design.
  • Tracked dependencies across DBA, backend developers, and infrastructure up to testing.
FIG 02 · Approval & Validation SwimlaneSanitized BA flow
REQUESTER

01 · Submit entry

Complete form fields and required attachments.

If returned: revise draft and resubmit.
SYSTEM

02 · Validate rules

Verify required fields, role permissions, and duplicates.

When approved by reviewer: record status & audit log.
REVIEWER

03 · Approval gate

Approve submission or return with revision notes.

Decision gate routes the final workflow state.

Documents produced

  • BRD & FSD
  • Process Flowcharts & Use Cases
  • Low-Fidelity Wireframes
  • Test Cases & Status Reports

SIT, UAT & go-live

Checked test data with basic SQL, coordinated SIT and UAT runs, and handed over user manuals.

Outcome

Turned multi-unit reporting requests into documented specs, tested builds, and a completed production handover. TODO(owner): Add verified quantitative impact if available.

Takeaway

Reviewing rough wireframes with users catches missing fields and edge cases long before UAT.